Saturday, May 9, 2009

Additional water sump tank

Installation of additional 3000 litres water sump tank is completed.Man hole cover of the earlier sump tank is also replaced

Tuesday, May 5, 2009

Our Blogs on Kerala Architecture, House construction, interior design, Kerala life, travel and politics

Completed works
http://kerala-houseconstruction-irinjalakuda.blogspot.com/
http://kerala-houseconstruction-cochin.blogspot.com/
Work in progress
http://kerala-houseconstruction-vyttila.blogspot.com/
http://kerala-houseconstruction-nilambur.blogspot.com/
http://kerala-houseconstruction-ranni.blogspot.com/
http://kerala-houseconstruction-josephneroth.blogspot.com/
http://kerala-houseconstruction-sunny.blogspot.com/
http://kerala-houseconstruction-cherthala.blogspot.com/
http://kerala-houseconstruction-elamakkara.blogspot.com/
http://tamilnadu-houseconstruction-ootty.blogspot.com/
Blog and Knoll on Kerala Architecture
http://knol.google.com/k/thomas-viruvelil/kerala-architecture/
http://kerala-architects.blogspot.com/
Blog on Kerala life, Politics, travel and on Kerala Architecture
http://kerala-life.blogspot.com/
DISCLAIMER
Every effort is taken to provide you authentic information on Kerala Architecture and it is features and other relevant information on building a house in Kerala. VIRUVELIL group of Companies or V.H.Thomas or any person interacting through this website on behalf of VIRUVELIL group of companies will not be responsible for the authenticity or correctness of the information provided through this website or conveyed by email to any person contacting us for information, assistance, guidance or for any commercial activity related or followed after any enquiry or request for services /assistance/guidance
We do not accept responsibility for loss or damage arising from the use of the information provided through this website which may be creative work/technical data without our consent/involvement and guidance. We have complete, unchallenged copy right for all information, data, pictures, design details provided through this website. Any dissemination, use, review, distribution, printing or copying in part or full of information, data, pictures design details provided through this website is strictly prohibited.

Saturday, May 2, 2009

Installing additional water sump tank


Additional water sump tank of 3000 litres is installed close to existing water sump tank and inter connection is also done.Picture shows work in progress

Friday, March 6, 2009

Interior wood work
















Interior wood work is nearing completion.Some pictures of stair posts,hand rails and master post with carvings can be seen

Thursday, February 12, 2009

Cup boards and dressing table




Pictures shows cupboards in bed rooms and dressing table portions with woodden carvings being kept at site for interior work

Friday, February 6, 2009

Interior wood work in progress







Pictures shows interior wood work in progress for Kitchen,Work area and Living room panelling

Thursday, January 29, 2009

Fixing of cast iron gates







One Cast iron main gate of width 14 feet and another cast iron wicket gate of width 2.5 ft were fixed on concrete pillars of size,50 cmx 50 cm(three nos) after excavating the area for about 4 feet(120 cm).Old rubble work in the area well packed and tight due to continuous lorry runs for construction were completely removed to ensure proper concrete footing and base for the gate pillars.As the gates were very heavy,it was a tough job with more man power working for about a week to get the gate fixed in position along with concreting of support pillars.



Gates were raised sufficiently up from the ground level by about 23cm to take care of future level raising of the road in front.Picture show the gates immediately after fixing