Work on gate pillars with bamboo design tiles started.Pictures showwork in progress.Water connection obtained and connection done today,26/11.KSEB inspection over and payment for three phase regular connection will be done next day
3600sft two storeyed house facing lake at Vyttila,Cochin being constructed by Viruvelil group For Mr.Binu Thomas working at Botswana,Africa
Thursday, November 26, 2009
Saturday, November 21, 2009
Painting work nearing completion
Painting work is nearing completion.Solar water heater reached site and is being installed
Pictures follows.